Difference between revisions of "B4 - Demonstration run"

From Sea
Jump to: navigation, search
m
Line 12: Line 12:
 
== Description and methods employed (what, how, where and when) ==
 
== Description and methods employed (what, how, where and when) ==
  
Describe in details the content of the action. There must be a clear link between the action and the project's objective. Indicate what will be done, how, where and when.
+
After
  
 
== Constraints and assumptions ==
 
== Constraints and assumptions ==
 +
* Constraints
 +
** Execution must be completed on schedule in order to leave significant time to demonstration of running process.
 +
* Assumptions
 +
** Equipments supply and installation does not face unforeseen, blocking issues
 +
** No disrupting organizational change will occur in suppliers organizations
 +
** Turnover of key project resources is low.
 +
** Delays on critical path may be handled by careful monitoring and control by project management. Buffer time allocated in planning is enough.
  
Indicate what may prevent you from implementing the action as planned and what will be done to address this risk. Please ensure that these constraints and assumptions are in line with those indicated on Form B5.
 
  
 
== Beneficiary responsible for implementation ==
 
== Beneficiary responsible for implementation ==
  
Please indicate which of the project's beneficiaries will be in charge of the implementation of each action. Should more than one beneficiary be implicated, please give full details of which beneficiary is responsible for what.
+
P1 - SEARIS
 +
 
  
 
== Expected results ==
 
== Expected results ==
  
 
Please indicate (preferably in bullet points) the quantified/measurable results/outputs from the action. Please indicate whether they will be used in other actions and how.
 
Please indicate (preferably in bullet points) the quantified/measurable results/outputs from the action. Please indicate whether they will be used in other actions and how.
 +
 +
== Where and when  ==
 +
This action will mainly take place at COWS plant site in Viareggio.
 +
 +
Action start: 01/09/2015
 +
 +
Action end: 28/04/2016
  
 
== Indicators of progress ==
 
== Indicators of progress ==

Revision as of 11:56, 15 July 2011

B4 - Demonstration run
Set-up of agreements with users of generated power
Management at demonstration scale
Continuous monitoring and display of performances
Fine-grained adjustement of all process blocks
COWS model documentation
D6  - COWS model and process handbook

Description and methods employed (what, how, where and when)

After

Constraints and assumptions

  • Constraints
    • Execution must be completed on schedule in order to leave significant time to demonstration of running process.
  • Assumptions
    • Equipments supply and installation does not face unforeseen, blocking issues
    • No disrupting organizational change will occur in suppliers organizations
    • Turnover of key project resources is low.
    • Delays on critical path may be handled by careful monitoring and control by project management. Buffer time allocated in planning is enough.


Beneficiary responsible for implementation

P1 - SEARIS


Expected results

Please indicate (preferably in bullet points) the quantified/measurable results/outputs from the action. Please indicate whether they will be used in other actions and how.

Where and when

This action will mainly take place at COWS plant site in Viareggio.

Action start: 01/09/2015

Action end: 28/04/2016

Indicators of progress

Please indicate how progress of this action will be measured. The descriptions may be accompanied by explanatory graphs, tables or pictures which may be included in the forms by using the “Pictures” check box.