B4 - Demonstration run
 
B4 - Demonstration run
Set-up of agreements with users of generated power
+
Set-up of agreements with users of generated heat
 
Management at demonstration scale
 
Management at demonstration scale
 
Continuous monitoring and display of performances
 
Continuous monitoring and display of performances
Fine-grained adjustement of all process blocks
+
Fine-grained adjustment of all process blocks
 
COWS model documentation
 
COWS model documentation
 
D6  - COWS model and process handbook
 
D6  - COWS model and process handbook
Line 12: Line 12:
 
== Description and methods employed (what, how, where and when) ==
 
== Description and methods employed (what, how, where and when) ==
  
The action of running the plant with demonstration goals
+
The last part of COWS project is devoted to enhance the demonstration aim of the project by:
 +
* running in "showcase mode" allowing interested parties (professionals, utility managers, environmental scholars and activits, CSOs, etc.) to understand better how the COWS approach solved an environmental problem in Viareggio and how to replicate or transef it;
 +
* opening to further improvements that require contributions from new partners, such as:
 +
** involvement of neighboring greenhouses for full heat exploitation;
 +
** collaboration with engineering teams for further fine-grained tuning of COWS pre-treatment and all process blocks;
 +
** amking COWS log data available to research centres that may use them as real world test-case corpora;
 +
 
  
 
After  
 
After  

Revision as of 14:05, 15 July 2011

B4 - Demonstration run
Set-up of agreements with users of generated heat
Management at demonstration scale
Continuous monitoring and display of performances
Fine-grained adjustment of all process blocks
COWS model documentation
D6  - COWS model and process handbook

Description and methods employed (what, how, where and when)

The last part of COWS project is devoted to enhance the demonstration aim of the project by:

  • running in "showcase mode" allowing interested parties (professionals, utility managers, environmental scholars and activits, CSOs, etc.) to understand better how the COWS approach solved an environmental problem in Viareggio and how to replicate or transef it;
  • opening to further improvements that require contributions from new partners, such as:
    • involvement of neighboring greenhouses for full heat exploitation;
    • collaboration with engineering teams for further fine-grained tuning of COWS pre-treatment and all process blocks;
    • amking COWS log data available to research centres that may use them as real world test-case corpora;


After

Constraints and assumptions

  • Constraints
    • Execution must be completed on schedule in order to leave significant time to demonstration of running process.
  • Assumptions
    • Equipments supply and installation does not face unforeseen, blocking issues
    • No disrupting organizational change will occur in suppliers organizations
    • Turnover of key project resources is low.
    • Delays on critical path may be handled by careful monitoring and control by project management. Buffer time allocated in planning is enough.


Beneficiary responsible for implementation

P1 - SEARIS


Expected results

Please indicate (preferably in bullet points) the quantified/measurable results/outputs from the action. Please indicate whether they will be used in other actions and how.

Where and when

This action will mainly take place at COWS plant site in Viareggio.

Action start: 01/09/2015

Action end: 28/04/2016

Indicators of progress

Please indicate how progress of this action will be measured. The descriptions may be accompanied by explanatory graphs, tables or pictures which may be included in the forms by using the “Pictures” check box.