Difference between revisions of "Index:LIFE"
m (→Monitoring actions) |
(→Communication and dissemination actions) |
||
| Line 45: | Line 45: | ||
===[[:Category:Communication and dissemination actions|Communication and dissemination actions]]=== | ===[[:Category:Communication and dissemination actions|Communication and dissemination actions]]=== | ||
| − | [[D1-Project web site|D1-Project web site]] | + | [[D1-Project web site|D1-Project web site]] --> OK DONE |
| − | [[D2-LIFE information boards|D2-LIFE information boards]] | + | [[D2-LIFE information boards|D2-LIFE information boards]] --> OK DONE |
| − | [[D3-Layman's Report|D3-Layman's Report]] | + | [[D3-Layman's Report|D3-Layman's Report]] --> OK DONE |
| − | [[D4-COWS communication campaign|D4-COWS communication campaign]] | + | [[D4-COWS communication campaign|D4-COWS communication campaign]] --> OK DONE |
| − | [[D5-COWS conferences/meetings|D5-COWS conferences/meetings]] | + | [[D5-COWS conferences/meetings|D5-COWS conferences/meetings]] --> OK DONE |
<hr> | <hr> | ||
Revision as of 19:25, 13 July 2011
Contents
Part A - administrative information
A1-Environment Policy ad Governance project application
A2-Coordinating beneficiary profile
A3-Coordinating beneficiary declaration
A4-Associated beneficiary declaration
A5-Associated beneficiary profile
A6-Co-financier profile and commitment form-->not available
A7-Other proposals submitted for European Union Funding
Part B - technical summary and overall context of the project
B1-Summary description of the project
B2-Environmental problem targeted
B3-Demonstration character of the project
B4-Stakeholders involved and main target audience of the project
B5-Expected constraints and risks related to the project implementation and how they will be dealt with
B6-Continuation/Valorisation of the project results after the end of the project
Part C - detailed technical description of the proposed actions
Preparatory actions
A1 - COWS plant & process design
A2 - Provisional contracting of sources & outputs
Implementation actions
B1 - Plant modification for COWS implementation
B2 - Build COWS prototype subsystem
Monitoring actions
C1 - Monitoring of the project impact on the main target audience
C2 - Monitoring of the impact on the environmental problem targeted
C3 - Assessment of the socio-economic impact of the project
Communication and dissemination actions
D1-Project web site --> OK DONE
D2-LIFE information boards --> OK DONE
D3-Layman's Report --> OK DONE
D4-COWS communication campaign --> OK DONE
D5-COWS conferences/meetings --> OK DONE
Project management and monitoring of the project actions
E1-Project management by SEA RISORSE S.p.A.
E3-Training, workshops and meeting for the beneficiaries
E5-After-LIFE Communication plan
C2-Deliverable products, milestones and activity reports foreseen of the project
C3-Timetable