Difference between revisions of "Index:LIFE"
(→Part B - technical summary and overall context of the project) |
(→Part B - technical summary and overall context of the project) |
||
| Line 13: | Line 13: | ||
[[B1-Summary description of the project|B1-Summary description of the project]]<br> | [[B1-Summary description of the project|B1-Summary description of the project]]<br> | ||
[[B2-Environmental problem targeted|B2-Environmental problem targeted]]--> '''TO ADD'''<br> | [[B2-Environmental problem targeted|B2-Environmental problem targeted]]--> '''TO ADD'''<br> | ||
| − | [[B3-Demonstration character of the project|B3-Demonstration character of the project]]<br> | + | [[B3-Demonstration character of the project|B3-Demonstration character of the project]]--> '''TO ADD''' <br> |
[[B4-Stakeholders involved and main target audience of the project|B4-Stakeholders involved and main target audience of the project]] --> '''TO ADD''' <br> | [[B4-Stakeholders involved and main target audience of the project|B4-Stakeholders involved and main target audience of the project]] --> '''TO ADD''' <br> | ||
| − | [[B5-Expected constraints and risks related to the project implementation and how they will be dealt with|B5-Expected constraints and risks related to the project implementation and how they will be dealt with]] | + | [[B5-Expected constraints and risks related to the project implementation and how they will be dealt with|B5-Expected constraints and risks related to the project implementation and how they will be dealt with]] |
[[B6-Continuation/Valorisation of the project results after the end of the project|B6-Continuation/Valorisation of the project results after the end of the project]] --> '''TO ADD'''<br> | [[B6-Continuation/Valorisation of the project results after the end of the project|B6-Continuation/Valorisation of the project results after the end of the project]] --> '''TO ADD'''<br> | ||
Revision as of 23:05, 16 July 2011
Contents
Part A - administrative information
A1-Environment Policy ad Governance project application -->OK
A2-Coordinating beneficiary profile SEARIS--> INSERT NEW DESCRIPTION PROFILE
A3-Coordinating beneficiary declaration SEARIS
A4-Associated beneficiary declaration SEAAMB
A4-2-Associated beneficiary declaration COMVIA
A5-Associated beneficiary profile SEAAMB--> INSERT NEW DESCRIPTION PROFILE
A5-2-Associated beneficiary profile COMVIA---> INSERT NEW DESCRIPTION PROFILE
A6-Co-financier profile and commitment form-->not available
A7-Other proposals submitted for European Union Funding--> '--> CHANGE DESCRIPTION TO ADD
Part B - technical summary and overall context of the project
B1-Summary description of the project
B2-Environmental problem targeted--> TO ADD
B3-Demonstration character of the project--> TO ADD
B4-Stakeholders involved and main target audience of the project --> TO ADD
B5-Expected constraints and risks related to the project implementation and how they will be dealt with
B6-Continuation/Valorisation of the project results after the end of the project --> TO ADD
Part C - detailed technical description of the proposed actions
Preparatory actions
A1 - COWS plant & process design --> OK DONE
A2 - Consultation of key stakeholders --> OK DONE
Implementation actions
B1 - Plant modification for COWS implementation--> OK DONE
B2 - Build COWS prototype subsystem --> OK DONE
B3 - Test run--> OK DONE
B4 - Demonstration run--> OK DONE
Monitoring actions
C1 - Monitoring of the project impact on the main target audience --> OK DONE
C2 - Monitoring of the impact on the environmental problem targeted --> OK DONE
C3 - Assessment of the socio-economic impact of the project --> DRAFT
Communication and dissemination actions
D1-Project web site --> OK DONE
D2-LIFE information boards --> OK DONE
D3-Layman's Report --> OK DONE
D4-COWS communication campaign --> OK DONE
D5-COWS conferences/meetings --> OK DONE
Project management and monitoring of the project actions
E1-Project management by SEA RISORSE S.p.A.--> OK DONE
E2-External Audit --> OK DONE
E3-Training, workshops and meeting for the beneficiaries --> OK DONE
E4-Networking activities--> OK DONE
E5-After-LIFE Communication plan --> OK DONE
C2-Deliverable products, milestones and activity reports foreseen of the project--> OK DONE
C3-Timetable--> OK DONE