Revision as of 22:55, 15 July 2011
Contents
Part A - administrative information
A1-Environment Policy ad Governance project application -->OK
A2-Coordinating beneficiary profile SEARIS-->OK PROFILE TO BE IMPROVED
A3-Coordinating beneficiary declaration SEARIS
A4-Associated beneficiary declaration SEAAMB
A4-2-Associated beneficiary declaration COMVIA
A5-Associated beneficiary profile SEAAMB-->OK PROFILE TO BE IMPROVED
A5-2-Associated beneficiary profile COMVIA-->OK PROFILE TO BE IMPROVED
A6-Co-financier profile and commitment form-->not available
A7-Other proposals submitted for European Union Funding--> NO OK TBR
Part B - technical summary and overall context of the project
B1-Summary description of the project
B2-Environmental problem targeted
B3-Demonstration character of the project
B4-Stakeholders involved and main target audience of the project OK DONE MAYBE TO BE IMPROVED
B5-Expected constraints and risks related to the project implementation and how they will be dealt with
B6-Continuation/Valorisation of the project results after the end of the project --> OK DONE MAYBE TO BE IMPROVED
Part C - detailed technical description of the proposed actions
Preparatory actions
A1 - COWS plant & process design --> OK DONE
A2 - Provisional contracting of sources & outputs --> OK DONE
Implementation actions
B1 - Plant modification for COWS implementation--> OK DONE
B2 - Build COWS prototype subsystem --> OK DONE
B3 - Test run--> OK DONE
B4 - Demonstration run--> UNDER REVISION
Monitoring actions
C1 - Monitoring of the project impact on the main target audience --> OK DONE
C2 - Monitoring of the impact on the environmental problem targeted
C3 - Assessment of the socio-economic impact of the project --> DRAFT
Communication and dissemination actions
D1-Project web site --> OK DONE
D2-LIFE information boards --> OK DONE
D3-Layman's Report --> OK DONE
D4-COWS communication campaign --> OK DONE
D5-COWS conferences/meetings --> OK DONE
Project management and monitoring of the project actions
E1-Project management by SEA RISORSE S.p.A.--> OK DONE
E2-External Audit --> OK DONE
E3-Training, workshops and meeting for the beneficiaries --> OK DONE
E4-Networking activities--> OK DONE
E5-After-LIFE Communication plan --> OK DONE
C2-Deliverable products, milestones and activity reports foreseen of the project--> OK DONE
C3-Timetable--> OK DONE